In Queensland, the days from 22 December to 10 January are not business days under the security of payment law. That makes the date of a December payment claim one of the most important cash decisions a builder makes all year. On the default terms, a claim given on Monday 7 December is due on Monday 21 December. The same claim given a week later, on Monday 14 December, is due on Friday 15 January.
Most builders know the break slows payments down. Fewer count what it does to their own claims, or to the bank balance between the last receipt before Christmas and the first one after it. Below we count both for an illustrative builder, then set out what to settle in November, while the dates can still change.
How the break moves the due date of a claim
Under the Building Industry Fairness (Security of Payment) Act 2017, a progress payment falls due 10 business days after the payment claim is given, unless the contract sets another date, and a payment schedule is due within 15 business days, or sooner if the contract says so. A business day excludes weekends, public holidays and every day from 22 December to 10 January. This Christmas, the last business day before the break is Monday 21 December 2026 and the first after it is Monday 11 January 2027.
On those default terms, a claim given on Monday 30 November is due on Monday 14 December. One given on Monday 7 December is due on Monday 21 December, the last business day before the break. One given on Monday 14 December is due on Friday 15 January, and one given on Monday 21 December on Friday 22 January. A claim given during the break counts as given on Monday 11 January and is due on Monday 25 January. That includes a claim given one day late, on Tuesday 22 December, and every claim tied to a 31 December reference date.
Reference dates decide when each claim can be given. The contract sets them, and where it is silent the default is the last day of each month. Only one claim can be given for each reference date, and a claim given before its reference date may be invalid, which may limit your access to adjudication. So most of the work done in December is paid in late January whatever you do. What you can change is how much of it the contract lets you claim before the break, and whether the November claim goes in on time. Given on 30 November, it is due on 14 December. Given a fortnight late, on 14 December, it is due on 15 January.
These dates matter most on commercial work and on the subcontracts beneath every job. Contracts with homeowners for domestic building work follow their own stage payments, so check what each of yours says.
What leaves the account while you wait
Construction cash flow over the break is easiest to see in one business. Take a Brisbane builder with 11 people on wages and most trades subcontracted, working on contracts with the default month end reference dates. Its November claims were paid on Monday 14 December and its November subcontractors on the same day, leaving $180,000 in the bank on Tuesday 15 December. Its December claims, for work up to 21 December, count as given on 11 January and are paid on Monday 25 January. Its subcontractors claim on the same month end dates, so their December claims fall due that same Monday. The business closes on Tuesday 22 December and reopens on Monday 11 January.
Six Thursday pay runs leave the account before the December money arrives. The three in the break, paid in the usual weekly cycle, cover ordinary time for 11 days of annual leave and three public holidays, with the 17.5 per cent loading the award adds to the leave days. Wages come to $126,300, including $7,200 of loading. Super at 12 per cent now follows every pay run, reaching each fund within 7 business days of payday, so the super for four pay runs, $9,840, goes before 25 January. Under the quarterly rules that ended on 30 June 2026, super for December was not due until 28 January. The November materials, $88,000 on 30 days from the end of the month, fall due on 31 December. Overheads run at $5,600 a week, $28,000 over the five Mondays to 18 January.
Together that is $252,140 going out while nothing comes in. The account drops below zero on Thursday 7 January and reaches its lowest point, $72,140 overdrawn, after the pay run on Thursday 21 January. It stays there until the claims are paid on Monday 25 January.
Now give one of its contracts an extra reference date in the first week of December, so that $230,000 of the December work can be claimed on Monday 7 December. That claim is due on Monday 21 December, the balance never falls below $153,400, and no overdraft is needed. The work, the wages and the suppliers stay the same in both cases.
Illustrative example, modelled on the default timeframes under the Act, the annual leave terms of the award and typical settings for a builder of this size. Not a client engagement. Figures exclude GST. A full plan uses your own contracts, pay cycle and supplier terms.
One more date sits behind the January receipts. The GST collected on November and December claims, less the GST on purchases, is due with the October to December BAS on 28 February. In 2027 that falls on a Sunday, so the payment moves to Monday 1 March, and part of the January money already belongs to the ATO.
What to settle in November
Give the November claim on its reference date. On the default terms, a claim given on 30 November is paid before Christmas, and a delay of a fortnight sends it to the middle of January.
Read the reference dates in every running contract. Where one allows a claim early in December, use it. Where none does, ask the client now whether they will agree to an extra December claim, and have your legal adviser put the change in writing, because a claim given before a reference date may be invalid.
Match the claim dates of your subcontractors to your own. If your subcontractors claim on the 21st and you can only claim at month end, you pay them on Friday 22 January and are paid on Monday 25 January.
Decide how the leave is paid. The building award requires annual leave to be paid in advance, before the employee goes on leave, although staff paid by electronic funds transfer can be paid in their usual cycle. Either way the money leaves before the January receipts, and the choice only moves it between weeks.
Check where the shutdown notice stands. The award lets you direct staff to take accrued paid leave over a Christmas shutdown if you give them written notice two months ahead, or less notice where the majority of the staff affected agree. For a shutdown starting on 22 December, two months ran out on 22 October, so a builder who has not given notice needs that agreement. Leave without pay for anyone short of leave needs their written agreement too. Your adviser can confirm how the clause applies to your workforce.
Size the overdraft to the lowest point. A facility set for an average month will not cover a trough in the third week of January. Arrange it in November, before the December rush.
The same gap between earning and being paid runs through every project, as we set out in why a profitable project can still starve for cash. Our fractional CFO service builds this cash bridge with owners on their own contracts and pay runs, and every article we have written for builders and trades sits in the construction view of the blog library.
If you would like the gap worked out on your own claims and payroll before the break, book a discovery call.
Sources: Queensland Building and Construction Commission, Business days over the holiday period (published 28 November 2025), Request payment (published 31 August 2021) and Industry guide to security of payment laws (August 2022); Building Industry Fairness (Security of Payment) Act 2017 (Qld); Fair Work Commission, award MA000020, clauses 31.2 and 31.3, consolidated to 1 July 2026; Australian Taxation Office, super guarantee due dates (updated 21 April 2026) and BAS due dates (updated 17 September 2026). Business day counts are ours. All checked 21 October 2026.