Engineering and architecture firms · 7 min read

Fixed fee projects: tracking profit while the job is still running

Written by

On a fixed fee job, an engineering firm knows the fee it agreed and the hours booked so far. Owners ask us how to track fixed fee project profitability while the job is still running, before the final invoice settles it. Hours used against the budget cannot answer that alone: in the example below, one stage had used 76 per cent of its hours when its deliverables put it at 55 per cent complete.

The answer is worth most in the middle of the job. The fee was fixed at signing, so the only margin left to manage sits in the hours still to come. The earlier an overrun shows, the more margin a variation, a resourcing change or a conversation with the client can still recover.

Below we set out the tracker, work it through one design job from July to October 2026, and close with when to act and a monthly rhythm.

Fixed fee project profitability, stage by stage

Start from the fee proposal. Split the fee into the stages the job runs in, such as concept design, schematic design, design development and contract documentation, each with its fee and the budget hours the fee was built on. This works the same in an engineering firm or an architecture practice. Each agreed variation becomes a stage of its own, and timesheets need a code for every stage.

At each month-end, three figures come in. Hours used come from the timesheets. The share complete comes from deliverables: list the drawings, calculations, models and reports in the stage with their budgeted hours, add up the hours for those issued plus half for those under way, and divide by the budget hours of the stage. The estimate to complete comes from the person running the stage.

The tracker works out the rest. Fee earned is the stage fee times the share complete, and hours earned is the budget hours times the share complete. Burn is hours used divided by hours earned: at 1.00 a stage is using hours at the rate the fee assumed, and at 1.25 it is using a quarter more. Hours used plus the estimate to complete gives the forecast hours, and the fee less their full cost gives the forecast margin at completion.

Deliverables are what make this work: take the share complete from hours used instead, and every stage shows a burn of 1.00 until its hours run out. The method is a light form of earned value management, on which the Australian standard AS 4817:2019 gives guidance for projects of any size. To test an estimate to complete, multiply the budget hours still to be earned by the burn so far, and if the estimate is well below that figure, ask what will change.

One design job, tracked month by month

Illustrative example, modelled on a fixed fee structural and civil design job for a three storey office building in south east Queensland. Not a client engagement. Figures exclude GST. Each hour is costed at $129, an assumed full cost of an hour once salary, the 12 per cent super guarantee and overheads are spread over the hours the team can charge.

The engineering firm priced the job at $148,000 for 810 budget hours, in the same four stages as the architect on the project: $15,000 and 80 hours for concept design, $29,000 and 160 for schematic design, $43,000 and 235 for design development, and $61,000 and 335 for contract documentation. The planned cost of $104,490 leaves a margin of 29.4 per cent.

July ran close to plan. At the end of August, schematic design had closed at 186 hours against 160, a burn of 1.16, after two rounds of layout changes, and design development was 20 per cent complete on 66 hours, a burn of 1.40. The forecast margin had fallen to 23.9 per cent. The team expected to catch up, so nothing changed.

At the end of September the job had used 450 of its 810 hours, which left 360 and looked comfortable. Design development had used 76 per cent of its hours, and its deliverables put it at 55 per cent complete, a burn of 1.38. The fee earned was $67,650, 46 per cent of the fee, for 56 per cent of the budget hours. Mid month the client had asked for a rooftop plant platform, and 18 hours went on it before anyone priced it. The estimates to complete came to 490 hours, 50 of them for the platform. That is 130 more than the budget had left, for a forecast of 940 hours and a margin of 18.1 per cent.

In the first week of October the firm made three changes. It priced the 50 hours of platform work still to come as a variation of $9,500, which the client signed. It moved an experienced drafter onto the documentation drawings, with the engineer checking them, cutting that estimate by 30 hours. And it asked the client and the architect to fix the layouts from 9 October, with later changes priced as variations.

At the end of October design development had closed at 262 hours, four more than expected, documentation was 12 per cent complete on 38 hours, and the forecast stood at 914 hours for a fee of $157,500. The forecast margin at completion was back to 25.1 per cent. The 59 hours over budget in the three finished stages, $7,611 at cost and including the 18 platform hours, stay lost, because most of the work behind them was done before anyone acted.

When to act, and the monthly rhythm

We suggest acting when a stage runs at a burn above 1.10, or when the forecast margin falls more than five points below the margin the fee was priced at. In the example both signals showed at the end of August, a month before anything changed. Then match the action to the cause.

Added scope calls for a variation, priced before the work starts, because hours worked before the client agrees are hard to recover. Overruns on work the fee did cover call for a resourcing change, such as moving work from senior people to a drafter or graduate. Delays and changes from the client or other consultants call for a client conversation, figures in hand, about a cut-off date for changes or the information still owed.

The rhythm is monthly. Timesheets close on the last working day, coded to stage and variation. In the first week, each person running a stage updates its share complete and estimate to complete, and the principals review the jobs past a trigger. The same figures compare the fee earned with the fee invoiced on every job, so each stage is billed as soon as it is reached. When a job closes, its final hours by stage become the starting point for the next fee proposal.

Common questions

Who should judge how much of a stage is complete?

The person running the stage, against the deliverables list agreed at the start, with a principal reviewing the figures each month. The half credit rule for work under way keeps the judgement consistent from month to month, and the share complete never comes from the hours used.

What if the client will not agree to a variation?

Then the added hours are a cost of keeping the client, and the tracker shows what that cost is before the next request. Whether added work can be charged depends on how your agreement describes the scope and any additional services, so record each request, its date and the hours it took. Your legal adviser can confirm what your agreement allows.

Can we run this in a spreadsheet?

Yes. One row for each stage and each variation is enough, as long as timesheets are coded to stage. The share complete and the estimate to complete are entered once a month, and the rest is arithmetic. Our fixed fee project tracker does the same sums for one job: it takes the fee, the budgeted hours, the full cost of an hour and the work done so far, and shows the margin at completion and the hours left before the job starts to lose money.

Our page on fractional CFO support for engineering and architecture firms sets out how we work with design practices, and why fixed fee work hides margin covers how overruns stay out of sight. The realisation rate in engineering and architecture firms measures how much of the time worked turns into fees. Scope given away without a variation works like a discount, and our pricing and discount leakage check shows what discounting costs across a year. Every article we have written for professional services firms sits on the professional services articles page.

Book a discovery call to work through fixed fee project profitability on your own figures.

Sources: Australian Taxation Office, Super guarantee (last updated 17 April 2026) and How much super to pay (last updated 25 February 2026); Standards Australia, AS 4817:2019 earned value management, store listing (published 20 August 2019). All checked 28 October 2026.