A specialist subcontractor with several jobs running has a retention to watch on each one. Each head contractor holds a slice of every claim, each job reaches practical completion on its own date, and each defects period ends a year or so later. Take a waterproofing subcontractor working on eight jobs for four head contractors. Together those builders hold $181,750 of its money, and $24,000 of that is already due back.
The owner wants to know which retentions are due, when each one lands, and what it costs when a release runs late. A register of subcontractor retentions across every job answers all three. Below we set out the rules that shape it, build one for that subcontractor, and show what three months of delay does to its cash in 2027.
What a head contractor can hold, and when it must pay
Queensland law caps retention on a subcontract. Before practical completion, the retention withheld and any security held together can be no more than 5 per cent of the subcontract price, and no single payment can have more than 10 per cent withheld. After practical completion the cap falls to 2.5 per cent, so a subcontract holding the full 5 per cent has to release half at that point. Where a contract does not provide for release at the end of an identifiable period, the retention must be released 12 months after practical completion.
The head contractor must release retention in line with the contract, and failing to do so without a reasonable excuse is an offence, except for amounts in dispute or paid into court. In the 10 business days before a defects period ends, it must also give you a notice in the approved form stating the date the period ends, the amount it will pay if no defects need fixing, and the date it proposes to pay. Where your defects period is tied to the head contract and the head contractor is notified late, it has 5 business days from its own notice. A notice that never arrives is the first sign a release is about to slip.
Some retention also sits in trust. Where a project needed a project trust account, which covers most Queensland Government contracts of $1 million or more and most other contracts of $10 million or more, a head contractor holding cash retention from you must keep it in a retention trust account. Below those thresholds, no trust is required.
The caps, release and notice rules come from the Queensland Building and Construction Commission Act and the trust rules from the Building Industry Fairness (Security of Payment) Act, and exceptions apply, for example to amounts held against something paid for but not yet installed. Your legal adviser can confirm how they apply to each of your contracts.
One register across eight jobs
The register needs eight facts for each job: the head contractor, the subcontract price, the retention held today, the date of practical completion, the date the defects period ends, the window in which the notice should arrive, the amount and due date of each release, and whether the money sits in a retention trust. Every release then has a date in the diary.
For our subcontractor, as at 1 November 2026, the eight subcontracts total $5,080,000. Each withholds 10 per cent of every claim until 5 per cent of the price is held, releases half at practical completion and the rest when a 12 month defects period ends. Five jobs have reached practical completion and three are still running.
Two amounts are due now. The first job reached practical completion on 15 September 2025, so its defects period ended on 15 September 2026 and its last $10,500 should have been paid in October. No notice arrived in the first half of September, and nobody chased it. The fifth job reached practical completion on 30 September 2026, so half of its $27,000 retention, $13,500, was claimed in October and is due this month.
Across 2027, seven releases worth $116,500 fall due: $17,000 in January, $19,000 in February, $30,000 in April, $37,000 in July and $13,500 in October. The January release is half of the sixth job, which reaches practical completion in December. Another $50,000 follows in 2028, once the last three defects periods end.
Now suppose every 2027 release arrives three months late. At the 7.42 per cent average rate on variable small business loans in August 2026, carrying the money costs about $2,160 over the year. The delay also moves the money in time. Releases expected in the first half of 2027 fall from $66,000 to $36,000, and the $13,500 due in October moves into 2028. A subcontractor that planned its June quarter around the April releases finds $30,000 missing until July.
Illustrative example, modelled on the retention limits in the Act and typical subcontract terms for a business of this size. Not a client engagement. Figures exclude GST. A full register uses your own subcontracts and payment records.
Keeping the register working
Record practical completion on the day it is certified, and get the certificate or the written notice that confirms it. The defects period, the release dates and the notice window all count from that date.
Diary the notice window for every job. If the notice has not arrived by the end of the defects period, ask the head contractor for it in writing that day.
Claim each release on the date the contract allows, through the payment claim process the contract sets out, and keep a dated copy of each claim.
Reconcile the register against every payment schedule and remittance each month. Retention shown on a statement and retention in your register should agree to the dollar.
Ask each head contractor whether your retention sits in a retention trust, and note the answer. It tells you which of your money is held in a trust for your benefit.
Plan cash on the dates the money is likely to arrive. If releases from a head contractor usually run late, the register should say so, and the cash flow forecast should use the later date.
Builders see the same money from the other side, as we set out in the June gap, and retention is one reason a profitable project can still starve for cash. Our Trapped Cash tool shows how much of your working capital is tied up, and our fractional CFO service can build and keep a register like this one with you. Every article we have written for builders and trades sits in the construction view of the blog library.
If you would like your retentions mapped across every job and head contractor, book a discovery call.
Sources: Queensland Building and Construction Commission Act 1991 (Qld), sections 67L, 67M, 67N, 67NA, 67NB and 67NC, and Building Industry Fairness (Security of Payment) Act 2017 (Qld), chapter 2, current versions on the Queensland legislation site; Queensland Building and Construction Commission, Retentions and securities (published 20 February 2024), Planning a trust account (published 28 January 2024) and Pausing the further rollout of trust accounts (published 10 February 2025); Reserve Bank of Australia, statistical table F7, business lending rates (published 8 October 2026). All checked 21 October 2026.